Weekly Lane Closure Report for Friday July 30 through Friday August 6

Traffic Alerts

Traffic Alerts related to the HRBT Expansion Project are available below.

07/23/2021:  Weekly Lane Closure Report for Friday July 30 through Friday August 6


For news on other VDOT programs, visit VDOT's Newsroom.

For updates on current traffic or to view VDOT's traffic cameras, visit 511Virginia.org.

Weekly Lane Closures

As part of the HRBT Expansion Project construction crews will implement weekly lane closures, detours and traffic pacing on local roads, I-64 and the Hampton Roads Bridge-Tunnel. Travel restrictions include possible delays, reduced speeds and detours in some areas. Lane closure, detours and traffic pacing are subject to change based on weather conditions and other factors.

Ongoing Traffic Alerts

06/03/2021 - West Evans Street Closure and Detour Begins Early June. Read more...

12/07/2020 - NORFOLK  - Right turn lane closed on West Bay Avenue near the I-64 east on-ramp

Ongoing Construction Alerts

07/16/2021

Traffic Signal Work at Mallory Street Bridge to Impact Traffic. Construction crews continue work on traffic signal relocation, as part of the Mallory Street bridge replacement project, this afternoon/evening and overnight.  Read more...

7/07/2021
Willoughby Bay Bridge, Norfolk - Pile driving acitvities to begin as early as Wednesday, July 7. Read more...

06/15/2021
West Evans Street, Norfolk - Construction at West Evans Street in Norfolk beginning as early as Wednesday June 16.  Read more...

05/27/2021
Recreational boaters and others participating in marine sports and activities need to be aware of the ongoing construction work this Memorial Day weekend and throughout the summer (including the presence and activity of barges, cranes, crew boats, pile driving, etc.).  Read more...

04/16/2021
HAMPTON - The Hampton Roads Bridge-Tunnel Expansion Project (HRBT) will begin pile driving activities between the HRBT North Island and Hampton shoreline from mid- April 2021 to July 2021. Read more...

Mallory Street Bridge Construction

The Hampton Roads Bridge-Tunnel Expansion Project is underway covering nearly 10 miles between Settlers Landing Road in Hampton and the I-564 interchange in Norfolk. The construction of a new Mallory Street Bridge is part of the HRBT Expansion Project. Construction will happen in stages over two years in order to keep the existing bridge open.

Mallory Street Bridge Construction Fact Sheet

Completed Traffic Alerts

03/23/2021

NORFOLK – Traffic shifts began in late March as part of the HRBT Expansion Project's first phase of roadway widening in Norfolk near 4th View Street. Motorists are advised to stay alert to new traffic patterns. Read more... 

03/18/2021

NORFOLK - The right travel lane and shoulder on I-64 East and West between 4th View Street (exit 273) and Patrol Road (before exit 276) will be closed overnight beginning as early as Monday, March 22. Read more...

03/12/2021

Overnight lane closure on I-64 West before Bay Avenue in Norfolk. 
The right lane on I-64 West will be closed from Friday, March 12 at 9 p.m. until Saturday, March 13 at 7 a.m. for roadway repairs near the Evans Street overpass. 

HRBT Expansion Project Logo VDOT Logo Transportation Authority Logo HRBT Expansion Project Logo VDOT Logo Transportation Authority Logo HRBT Expansion Project Logo VDOT Logo Transportation Authority Logo HRBT Expansion Project Logo VDOT Logo Transportation Authority Logo HRBT Expansion Project Logo VDOT Logo Transportation Authority Logo HRBT Expansion Project Logo VDOT Logo Transportation Authority Logo HRBT Expansion Project Logo VDOT Logo Transportation Authority Logo HRBT Expansion Project Logo VDOT Logo Transportation Authority Logo HRBT Expansion Project Logo VDOT Logo Transportation Authority Logo HRBT Expansion Project Logo VDOT Logo Transportation Authority Logo HRBT Expansion Project Logo VDOT Logo Transportation Authority Logo